HOW TO IDENTIFY AND FIX PRODUCTION DELAYS

By Pascal Pollet – Sirris, Belgium

Are you struggling with production delays? The longer you wait to take action, the harder it becomes to catch up. But how can you spot a real delay—and address it effectively?

Seeing the Bigger Picture: Real versus Apparent Delays

Backlogs often occur at workstations that are already operating near full capacity. With little or no reserve capacity available, even a minor backlog can quickly escalate into a persistent problem. That’s why it’s essential to have an early and reliable warning signal — enabling you to take timely action and prevent the backlog from dragging on for weeks or even months.

At first glance, an order may seem late if it finishes at a workstation later than planned. In reality, however, this doesn’t necessarily mean there’s a problem — there may still be enough time downstream for the order to be completed and delivered on schedule.

Focusing blindly on the planned completion date at each workstation creates apparent delays: orders that appear critical but aren’t. The result? Unnecessary overtime or weekend work, along with frustration among employees who see the order sitting idle at the next step anyway.

That’s why delays should always be viewed from a broader perspective — not per workstation, but across the entire production chain, taking into account the expected delay throughout the whole process.

Calculating the Delay

A surprisingly simple method makes it possible to estimate an order’s delay accurately. The method is based on the following formula:

Expected delay = Required lead time − Remaining time until delivery date

  • Expected delay ≤ 0: the order can still be completed on time — no action needed.
  • Expected delay > 0: the order is at risk of being late — action required.

The required lead time consists of the sum of two components:

  • The remaining processing time of the order itself
    These are the operations that the order still needs to go through.

  • The waiting time caused by preceding orders with higher delivery priority
    This waiting time can be calculated in two steps:

    1. Determine the open workload at each workstation the order still needs to visit. This workload is the sum of the remaining processing times of all preceding orders — both those already at the station and those still on their way.

    2. Divide that workload by the expected throughput of the workstation.

The workstation with the longest calculated waiting time is identified as the dominant station. The total waiting time caused by all preceding orders is equal to the calculated waiting time of this dominant station. The waiting times at the other stations are effectively masked by it and can thus be disregarded.

At first, this may seem counterintuitive, as one might expect the total waiting time in the system to be the sum of the waiting times at all stations. However, this is not the case for two key reasons. First, the calculated waiting times already take into account the workload of orders currently being processed at each workstation, as well as those en route to it.

Second, it is important to realize that all workstations operate simultaneously on the workload of preceding orders. As a result, the overall workload in the system decreases in parallel across stations. By the time the dominant workstation has completed all preceding orders, the other stations will have cleared their corresponding workloads as well—meaning their effective waiting times will be zero.

For example, consider an order that moves from the dominant workstation to the next one in the routing sequence. By the time this order has been processed at the dominant workstation, the queue of preceding (and therefore more urgent) orders at the next workstation will have been completely cleared. As a result, the order will arrive at the next workstation as the first in line for processing, resulting in a negligible waiting time.

Example: Calculating a delay

Order X still needs to pass through stations A, B, and C. The remaining processing time for the order is 1 day, and the delivery is due in 8 days.

  • Station A: 35 hour workload, throughput 7 hours/day → 5 days
  • Station B: 70 hour workload, throughput 7 hours/day → 10 days
  • Station C: 96 hour workload, throughput 16 hours/day → 6 days

Station B has the longest calculated waiting time and is therefore the dominant station, determining the waiting time for the order.

  • Total lead time = 1 day + 10 days = 11 days
  • Remaining time until delivery date = 8 days
  • Expected delay = 11 – 8 = 3 days

If no action is taken, this order will be 3 days late. The only effective intervention is at station B, where the delay originates. For an order that only passes through stations A and C, station C may become the dominant one instead. This illustrates that multiple dominant stations can exist within a factory, depending on the routing.

Where and How to Take Corrective Action

The first intervention for a late order should always take place at the dominant workstation — the one with the longest waiting time. If sufficient improvement can be made there, the next step is to verify whether the waiting times at the other workstations remain within the available time before delivery.

Possible actions include:

  • Adding extra capacity (e.g., bridging breaks, working overtime, or assigning additional staff),
  • Shifting work to other workstations or outsourcing part of the work,
  • Organizing express transports to make up for lost time,
  • Discussing options with the customer (e.g., partial deliveries).

Clear Rules Make the Difference

Large delays are often difficult to recover from. That’s why it’s crucial to detect small delays early and respond immediately — before valuable time is lost. This can be achieved by generating daily reports that visualize both the delays and the dominant workstations. To enable quick and effective action, clear rules must be in place beforehand, so that catching up on delays becomes an almost automatic process.

A good example comes from Scania’s truck factory in Zwolle. There, any accumulated delay is made visible directly on the production line. As soon as the backlog reaches 12 trucks (about 50 minutes behind schedule), everyone works one hour longer the next day. This simple rule keeps delays consistently under control.

Conclusion

Production delays are inevitable — but they don’t have to be unmanageable. By calculating required lead times, assessing schedules from a global perspective, and establishing clear rules for corrective action, you can keep your production flow under control. This approach prevents stress, avoids unnecessary overtime, and keeps your customers satisfied.